Browse PIP Practices

Review the most up-to-date collection of PIP Practices. Most recently published practices are listed first. Search key terms or filter by discipline to narrow the list.
  • Reset
Found 581 Results
Icon for
Pipeline Systems
PLX09CS0S01

Pipeline Systems ASME B31.8 Material Specification 9CS0S01, Class 900, Carbon Steel, C.A.-None, Sour, Design Factor = 0.6

Abstract ↓

Not applicable

December 2021
New Practice
Icon for
Pipeline Systems
PLX15CS0S01

Pipeline Systems ASME B31.8 Material Specification 15CS0S01, Class 1500, Carbon Steel, C.A.-None, Sour, Design Factor = 0.6

Abstract ↓

Not applicable

December 2021
New Practice
Icon for
CSA
CVS02100

Site Preparation, Excavation, and Backfill Specification

Abstract ↓

This Practice describes the requirements for excavation, placement, inspection, and management of materials during the site preparation, excavation, and backfill phase of a construction project.

December 2021
Technical Correction
Icon for
CSA
STS03601

Application of ACI 351.5-15, Specification for Installation of Epoxy Grout between Foundations and Equipment Bases

Abstract ↓

This Practice supplements ACI 351.5-15, Specification for Installation of Epoxy Grout between Foundations and Equipment Bases. Together, this Practice and ACI 351.5-15 provide requirements for supplying, testing and installing epoxy grout materials. The requirements of ACI 351.5-15, as modified and supplemented by this Practice, are adopted by this Practice for supplying, testing and installing epoxy grout materials.

December 2021
Complete Revision
Icon for
CSA
STS03601M

Application of ACI 351.5M-15 Specification for Installation of Epoxy Grout between Foundations and Equipment Bases (Metric)

Abstract ↓

This Practice supplements ACI 351.5M-15, Specification for Installation of Epoxy Grout between Foundations and Equipment Bases (Metric). Together, this Practice and ACI 351.5M-15 provide requirements for supplying, testing and installing epoxy grout materials. The requirements of ACI 351.5M-15, as modified and supplemented by this Practice, are adopted by this Practice for supplying, testing and installing epoxy grout materials.

December 2021
New Practice
Icon for
CSA
STS03600

Application of ACI 351.4-14, Specification for Installation of Cementitious Grouting between Foundations and Equipment Bases

Abstract ↓

This Practice supplements ACI 351.4-14, Specification for Installation of Cementitious Grouting between Foundations and Equipment Bases. Together, this Practice and ACI 351.4-14 provide requirements for supplying, testing and installing nonshrink cementitious grout materials. This Practice is applicable for nonshrink cementitious grout materials installed between foundations and equipment and machinery bases as well as nonshrink cementitious grout materials installed between foundations and structural steel column bases. The requirements of ACI 351.4-14, as modified and supplemented by this Practice, are adopted by this Practice for supplying, testing and installing nonshrink cementitious grout materials.

December 2021
Complete Revision
Icon for
Piping
PNSMV025

Stainless Steel Check Valve Descriptions

Abstract ↓

This Practice provides requirements for suppliers providing stainless steel check valves included in PIP Piping Material Specifications (PMSs).

December 2021
Complete Revision
Icon for
Process Control
PCCIA001

Instrument Air Systems Criteria

Abstract ↓

This Practice provides requirements for designing instrument air systems that supply pneumatically actuated instruments and valves. This Practice describes the requirements for air quality, capacity, sizing, and testing of instrument air systems.

December 2021
Reaffirmation
Icon for
Process Control
PCEIA001

Instrument Air Systems Guidelines

Abstract ↓

This Practice provides guidelines for designing instrument air systems that supply pneumatically actuated instruments and valves. This Practice provides design guidelines for air quality, capacity, sizing, and testing of instrument air systems.

December 2021
Complete Revision
Icon for
Piping
PNSMV007

Carbon Steel Butterfly Valve Descriptions

Abstract ↓

This Practice provides requirements for suppliers providing carbon steel butterfly valves included in PIP Piping Material Specifications (PMSs).

December 2021
Complete Revision
Icon for
Piping
PNSMV006

Carbon Steel Ball Valve Descriptions

Abstract ↓

This Practice provides the detailed purchase descriptions for carbon steel ball valve tag numbers included in PIP Piping Material Specifications and used along with PIP PNSM0110 for the procurement of valves. This Practice also provides a cross reference for carbon steel ball valve tag numbers to applicable PIP Piping Material Specifications (PMSs).

December 2021
Technical Revision
Icon for
Piping
PN01SV0S01

Piping Material Specification 1SV0S01 Class 150, Alloy 254 SMO (UNS S31254), Socket Weld, C.A. – None, Process (PTFE Packing/Gaskets)

Abstract ↓

Not applicable

November 2021
Complete Revision
Icon for
Piping
PN03SV0S01

Piping Material Specification 3SV0S01 Class 300, Alloy 254 SMO (UNS S31254), Socket Weld, C.A.- None, Process (PTFE Packing/Gaskets)

Abstract ↓

Not applicable

November 2021
Complete Revision
Icon for
Machinery
RESP73H

Application of ASME B73.1 – 2020 Specification for Horizontal End Suction Centrifugal Pumps for Chemical Process

Abstract ↓

Scope The purpose of this Practice is to specify the requirements for design and manufacture of horizontal end suction centrifugal pumps. The requirements in this Practice are modifications, additions, and/or deletions (exceptions) to the requirements in ASME B73.1 - 2020. The section/paragraph numbers and the associated headings used in this Practice correspond to the ones used in ASME B73.1. Since this Practice does not take exception to all the requirements in ASME B73.1, the section/paragraph numbers in this Practice may not be sequential. Data sheets PIP RESP73 D and PIP RESP73-DM, appended, may be used to select options for ordering the pumps specified in this Practice. This practice is intended for chemical and hydrocarbon services and does not cover pumps sealed with packing. For general water services that fall out of the limitations of this practice use PIP RESP003H.

November 2021
Technical Revision
Icon for
Piping
PNSM0116

Purchasing Requirements for Piping and Pipeline Fittings & Flanges

Abstract ↓

This Practice describes the minimum requirements for the procurement of metallic pipe fittings and flanges.

November 2021
Technical Revision
Icon for
Electrical
ELEGL07

Electric Motor Voltage Dip Impact Mitigation

Abstract ↓

Electrical systems will experience electrical events in the form of voltage dips and outages. Depending on the magnitude and duration of these electrical events, electric motors can drop offline. The unexpected loss of an electric motor in a production unit can cause personnel safety issues, environmental issues, and loss profit opportunities (LPO). This Practice provides information which can be used to develop the basic premises on which to implement a voltage dip impact mitigation program to help overcome the adverse effects of production units dropping offline. The voltage dip impact mitigation program addresses the application of both under-voltage ride-through and under-voltage restart capabilities which should be added to the controls of electrical motors.

November 2021
New Practice
Icon for
Process Control
PCIPR100

Pressure Transmitter Installation Details

Abstract ↓

This Practice provides details for the installation of pressure transmitters in liquid, gas and steam services. This Practice contains installation details for pressure transmitters in liquid level service and includes details for electric or steam tracing of these installations. These details describe the base instrument installations. The bill of material provided with each detail is generic and is complementary to PIP PCSIP001- Instrument Piping and Tubing Systems Specifications

November 2021
Reaffirmation with Editorial Revision
Icon for
Electrical
ELSWC06

Nonshielded Power Cable Specification (2001 Volts to 5000 Volts)

Abstract ↓

This Practice describes the minimum technical requirements for design, material, construction, inspection, testing, purchase, and shipping of single and multiple conductor solid dielectric, insulated, nonshielded copper cable rated at 2001 volts to 5000 volts.

November 2021
Technical Revision
Icon for
Electrical
ELSWC07

Shielded Power Cable Specification (5 to 46 kV)

Abstract ↓

This Practice provides requirements for the purchase of single and multiple conductor shielded power cable rated at 5 kV to 46 kV. This Practice describes the minimum technical requirements for design, material, construction, inspection, testing, and shipping of solid dielectric, insulated shielded copper cable.

November 2021
Technical Revision
Icon for
Piping
PNSM0115

Purchasing Requirements for Piping and Pipeline Pipe

Abstract ↓

This Practice describes the minimum requirements for the procurement of metallic pipe.

November 2021
Technical Revision

Learn More About PIP Practices

Name(Required)
Select the document(s) you’d like to download.(Required)
This field is for validation purposes and should be left unchanged.